The Time Trakkr panel on a Jira issue used to show only what you had tracked. It now shows what Jira itself knows: logged in Jira, the original estimate, the remaining estimate, and how far through the estimate the work is.
Three deliberate choices in how those numbers are presented:
- Jira's total and your unsynced time are never added together. Jira works out its "logged" figure from worklogs, so it already contains everything Time Trakkr has sent. Adding your tracked total on top would double it. Time recorded here that has not reached Jira yet is shown on its own line instead, so you can see the gap rather than having it hidden inside a total.
- A missing estimate says "Not set". Not zero, and no progress bar. An issue nobody estimated is unestimated, not an issue with no budget that everything overruns.
- Durations are Jira's own wording. "2d" means different things on different Jira sites, depending on how long the site says a working day is — so the panel repeats what Jira says rather than working it out.